MADURAI: Engine trial run will be done on the Andipatti – Theni section on September 4th 2021. A press release here today from the Southern Railway Madurai Division had informed that it is proposed to conduct this engine trial run on the newly laid BG line between Andipatti and Theni railway stations, at a speed of 120 KMPH on Saturday (04.9.2021). This trial run will be conducted between 09.00 hrs and 18.00 hrs under the supervision of Mr.Suryamurthy, Dy.Chief Engineer, Construction, Madurai.  “Hence, the public in the vicinity are cautioned not to approach or cross the track during the said timings. This new section would have statutory inspection of Commissioner of Railway Safety during this month, after this speed trial run,” the press release added.